PUBLICATION OF THE AWARD OF CONSULTANCY CONTRACTS FOR THE DETAILED DESIGN AND SUPERVISION OF THE KWARA STATE AGRO-INDUSTRIAL HUB (AIH)
Publication of award of consultancy contract for the detailed design and supervision of Kwara State Agro-Industrial Hub (AIB).

Category: update
•Jul 28, 2025
PUBLICATION OF THE AWARD OF CONSULTANCY CONTRACTS FOR THE DETAILED DESIGN AND SUPERVISION OF THE KWARA STATE AGRO-INDUSTRIAL HUB (AIH)
Information Note
Publication Date: 28th July 2025
Country: Nigeria
Executing Agency: Kwara State Special Agro-Industrial Processing Zone Project
Name of Project: Special Agro-Industrial Processing Zone Project (SAPZ)
Mode of Financing: Service-Ijara
Financing No.: NGA 1040
Name of Request for Proposal: Engagement of Consultant for the Detailed Design and Supervision of Kwara State Agro-Industrial Hub (AIH)
Selection Method: Quality and Cost-Based Selection Method (QCBS)
REOI Publication Date: Monday, January 29, 2024
Issuance Date of RFP: 27th September 2024
Opening Date of Technical Proposal: 29th October 2024
Opening Date of Financial Proposal: 20th January 2025
Date of Approval by the Bank of Negotiated Draft Contract: 8th July 2025
1. The successful Consultant
Name: MESSER. BOLCON ASSOCIATES NIGERIA LIMITED
Nationality Nigerian
Address: Suite 6 & 7, Fundex House Behind Glory Tabernacle Church Bodija Ibadan
Contract Amount: ₦374,750,000.00
Contract Start Date: 24th July, 2025
Duration of Execution: 3 Months for Design Phase, 32 Month for Supervision and Defect Liability Period
Summary of the Purpose of Contract Selection of Consultant for the Detailed Design and Supervision of Kwara State Agro-Industrial Hub
2. Unsuccessful Bidders- Total of participated bidders (6)
Name of Consultants Nationality Overall Technical Score Financial Proposal Price Evaluated financial Proposal Combined Score & Ranking
A4 Associates Ltd
Nigeria Total Score= 58.48 NA NA NA
Alim & Associates Limited
Nigeria Total Score= 72.21 NA NA NA
Bolcon Associates Nigeria Limited
Nigeria Total Score= 76.64 N374, 750,000.00 N374, 750,000.00 81.58- 1st
Ovie Arup & Partners
Nigeria Total Score= 94.764 N2,500,295,893.15 2,500,295,893.15 74.823- 2nd
Morphosis
Nigeria Total Score= 75.64 N1, 183,426,200.00 N1, 183,426,200.00 64.65- 3rd
Tesda Group One-MDS(JV
Nigeria Disqualified NA NA NA
Signed
The State Project Coordinator,
Kwara State Special Agro-Industrial Processing Zone Project,